• Orion Power Khulna Ltd.

  • Orion Power Khulna Ltd.

Ongoing Progress : Orion Power Khulna Ltd.

  • Sand Filling is in progress.
  • Contracts for implementation:
    • BTG (Boiler, Turbine & Generator) contract has been signed with Alstom on 27th January, 2014.
    • SEPCO III has been finalized as EPC Contractor. Tentaive Contract signing date is December 2014.
  • Environment and Social Impact Assessment:
    • EIA Report Submitted to Department Of Environment.
    • 1stPresentation meeting held In DOE head Office on 12th August, 2014.
    • 2nd meeting between Sponsor’s ESIA Consultants AECOM & DOE technical committee held In DOE head Office on September 30, 2014.
    • As per requirement of DOE the final edited ESIA report resubmitted on 29th October, 2014. DOE clearance is highly expected within December 2014.
  • Thermal Plume:
    • Primary data for thermal plume completed by IWM on 4th February, 2014. (Scope included Bathymetric Survey, Topographical Survey, water level observation, discharge & current measurement, salinity & temperature measurement.)
    • Plume Modelinghas been completed by AECOM in Singapore and submitted to DOE.
  • River Modeling
    • Primary data for River Modeling completed by IWM on 4th February, 2014. (Scope included Bathymetric Survey, Topographical Survey & water level observation)
    • River Modeling is in progress by Bangladesh University of Engineering Technology. Draft report completed.
  • Geotechnical survey has been Completed. Total 23 nos. of borehole has been tested.